§ 12-180. Cell site removal.


Latest version.
  • Upon cancellation, revocation or denial of the permit required by this division, the requestor or permittee shall remove such designated cell site and any support structure as requested by the city. Such removal [is] to be completed within thirty (30) days from the date of cancellation, revocation or denial. At the end of thirty (30) days, the city may, at its option, have the cell site removed, with such costs being the responsibility of the permittee.

(Ord. No. 11O-06-126, § 1, 6-27-11)